§ 6.06.12. Procedures and fees.  


Latest version.
  • Reference chapters 1 and 12.

    1.

    Prior to the approval of the order for development activities, the applicant must submit copies of permit documents from state and/or federal agencies. Any person planning a development as defined in this ordinance, unless exempted, shall submit a stormwater management plan or an application for variance to the board of adjustment.

    2.

    An administrative permit fee for review of the management plan will be collected at the time the stormwater management plan is submitted. Reference chapter 12 of this ordinance.

    3.

    Within 30 days after submission of the completed stormwater management plan, the county engineer shall approve, with or without specified conditions or modifications, or reject the plan and shall notify the applicant accordingly. If the county engineer has not rendered a decision within 30 days after plan submission, he shall inform the applicant of the status of the review process and the anticipated completion date. If the plan is rejected the county engineer shall state reasons. It is not the responsibility of the county engineer to design an acceptable project.

    4.

    The stormwater management plan shall not be approved unless it clearly indicates that the proposed development will meet the performance objectives described in section 6.06.04 and the criteria and minimum design standards described in sections 6.06.05 through 6.06.11, except where a variance has been granted pursuant to section 6.06.02.

    5.

    Inspections: No stormwater management plan may be approved without adequate provision for inspection of the property. The initial inspection will be prior to approval of the stormwater management plan. For final inspection reference section 6.01.052.5.

    6.

    Appeals: Reference chapter 11 of this ordinance.