§ 4.01.05. Phased construction.  


Latest version.
  • The construction of any development project may be phased or staged so as to coincide with the phased or staged construction of infrastructure facilities so that levels of service for such facilities are maintained upon completion of each phase or stage of the development project.

(Ord. No. 11-01, § 2, 1-18-11)